Romania Iecea Mica-1 Work Over Rig to Mobilise Tomorrow

  • Workover Rig Mobilisation will commence on Friday 19 June 2020
  • Testing Operations are expected to commence approximately 7 days after mobilisation.
  • Testing Programme includes the installation of permanent production tubing and flow control equipment in the well, underbalanced perforation and production testing of the well.
  • Test Objectives are to determine the production capacity of the well and confirm the suitability of the gas composition for commercial sales.
  • After Testing the well will be shut in awaiting commercial production.
  • Gas Commercialisation